ABRIDGEMENT ON PROJECTS EXECUTED
| |
STAR
ORECHEM INTERNATIONAL PVT.
LTD. Nagpur |
| 1. |
Project
: DEP AND OXIME
PRODUCTION
|
|
Scope
of work :
Detail engineering,
utility calculations,
preparation of
P&I Diagram,
sizing and mechanical
design of equipment,
preparation of
equipment layout,
pipeline sizing,
utility freezing,
preparation of
specification
sheets for all
equipment as
well as for all
utilities, detail
engineering of
all equipment,
preparation of
bill of quantities,
procurement of
all materials,
fabrication and
erection of equipment,
mechanical commissioning,
process commissioning,
and handing over
the site.
Site supervision,
expediation of
the project,
progress monitoring,
and reporting
to the site from
the day one till
mechanical commissioning
of the project
|
| 2. |
STAR
ORECHEM INTERNATIONAL
PVT. LTD. Nagpur. |
|
Project
: GAS PLANT DEP
AND OXIME PRODUCTION
|
|
Scope
of work :
Detail engineering,
utility calculations,
preparation of
P&I Diagram,
sizing and mechanical
design of equipment,
preparation of
equipment layout,
pipeline sizing,
utility freezing,
preparation of
specification
sheets for all
equipment as
well as for all
utilities, detail
engineering of
all equipment,
preparation of
bill of quantities,
procurement of
all materials,
fabrication and
erection of equipment,
mechanical commissioning,
process commissioning,
and handing over
the site.
Site supervision,
expediation of
the project,
progress monitoring,
and reporting
to the site from
the day one till
mechanical commissioning
of the project
|
|